Project Description

Cloverleaf Center Condominium

Cloverleaf Center Condominium
Germantown, MD

Building Usage: Occupied Condominium

Number of Stories: Four (4) stories wood framed buildings

Number of Units: Six (6) of seven (7) buildings comprising 98 units

Construction Contract Value: $1.4 million

Type of Work: Roof replacement; structural wood framing repairs; sheathing replacement and repairs; installation of window, door, and deck flashings; weather resistive barrier installation; replacement of horizontal siding with new vinyl siding and synthetic PVC trim on wood framed structures.

SRG’s Role: SRG was retained to investigate various leak conditions throughout six (6) of seven (7) buildings.  SRG developed a design package to address improperly installed sheathing, repair structural members damaged and deteriorated as a result of water infiltration, roofing replacement, flashing and weather resistive barrier replacement, as well as siding and trim replacement.  Services included bidding and construction observation and contract administration.